Current Status:  Waiting for Surveyor to Submit Mylar to P&P Meeting

Latest Plat Status
Final Plat Name   Red Cliffs Park Phase 5
Final Plat Number   1665-10
Current Status   Waiting for Surveyor to Submit Mylar to P&P Meeting
Date Last Updated   03/05/2010
Plat Location   PLS
Title Report Expires   04/27/2010
Pre-Final Plat Preparation Review Complete   02/04/2010
Final Plat Concurrent Review Underway   02/12/2010
Returned Concurrent Review Comments to Surveyor  
(Surveyor to Submit Mylar to Plat and Plan Meeting)  
03/05/2010
Final Plat Staff Signatures Complete  
PC Approval Date  
CC Approval Date  
Digital File of Final Plat Received  
Water Conservancy District Documents Received  
Final Plat Recorded   

Comments   03/05/2010 Returned comments to surveyor. Ok to print and submit Mylar any time when ready.
03/03/2010 Concurrent Review is complete. Call Todd @ 627-4124 to schedule an appointment to get comments.
3/1/10 received comments from parks.
02/12/2010 plans distributed.
02/04/2010 Initial Review is complete. Ok to submit for concurrent review at the Plat and Plan Meeting held on Thursdays at 2:00.