Name   [Turn Group Home]
Number   Grading-41081
Drawing of Record Submitted   8/13/2009
Electronic Drawing of Record Submitted   8/13/2009
Final Grading Report Submitted   8/13/2009
Date Scheduled   8/17/2009


BUILDING PERMIT RELEASE APPROVALS
Power  
Water  
Waste  
Engineering  
City Development Engineer  
Landscaping  


FINAL INSPECTION RELEASE APPROVALS
Power   8/17/09 approved per Dennis Wright. Trench inspected by other. OK for inspection. 6/3/2010 Approved per Dennis Wright.. 1 year warranty
Water   8/17/09 corrections required per Kevin C. Need concrete around meter box with rebar. Need to check all valve, open. Backflow or irrigation and fire system need to be tested. 8/21/09 corrections required per Kevin C. No concrete around meter box. Finish punch list. 8/25/09 approved per Kevin C 6/8/2010 Approved per Darrin Judd..1 year warranty.. wire good 7/6/2010 Approved per Kevin Condie.. 1 year warranty
Waste   8/17/09 approved per Glen G. Sewer okay. 6/3/2010 Approved per Glen Garland.. 1 year warranty
Engineering   8/18/09 approved per Brandon W. 6/7/10 - 1 year warranty approved per Brandon W.
City Development Engineer   8/14/09 corrections required per Ken B. Recommend warning signs or reflector plates at both O/H power poles, on Ease side (see map). Electronic DWG of record OK. 8/21/09 approved per Ken B. 6/4/10 - 1 year warranty approved per Ken B
Landscaping   8/14/09 approved per Ken B. 6/4/10 - 1 year warranty approved per Ken B