Building Permit/Final Inspection Status |
| Name |
Washington Fields LDS 8th Ward |
| Number |
Grading-39111 |
| Drawing of Record Submitted |
4/10/2008 |
| Electronic Drawing
of Record Submitted |
4/10/2008..revised 4/24/08 |
| Final Grading Report
Submitted |
4/10/2008 |
| Date Scheduled |
4/15/2008 |
| BUILDING
PERMIT RELEASE APPROVALS |
| Power |
|
| Water |
|
| Waste |
|
| Engineering |
|
| City Development Engineer |
|
| Landscaping |
|
| FINAL
INSPECTION RELEASE APPROVALS |
| Power |
|
| Water |
4/18/08 approved per Carson Tait.
6/15/2009 Approved perCarson Tait.. 1 year warranty |
| Waste |
4/15/2008 Corrections required per Lee Kell.. Clean MH, grind inverts, caps on clean outs, no brass caps, use cast iron rings & cover, not a complete list
5/6/2008 Approved per Lee Kell.. MH leaking water in MH selaed for now, If problem later R&W will fix.
4/10/09 - 1 year warranty - corrections required per Lee Kell. 2 M/H leaking in water (marked with a W). Invert work on Washington M/H outfall (marked with an I). |
| Engineering |
4/16/08 Approved per Carlos Robles
4/13/2009 Approved per Carlos Robles.. 1 year warranty |
| City Development Engineer |
4/15/08 corrections required per Cathy H. Electronic DWG of record needs to be in one DWG. It also needs to show all drainage improvements for site. per Ken B. End of entrance is incomplete. Landscaping is incomplete. Stop signs are missing. Rock piles in parking lot, green sidewalks, detention area incomplete and ADA signage is incomplete.
4/25/08 corrections required per Cathy H. Electronic DWG of record needs to show all drainage improvements as per approved plans.
5/2/2008 Approved per Ken Bricker
4/2/09 - 1 year warranty (check only 3000 E St Improvements - Approved per Ken B. |
| Landscaping |
4/15/08 corrections required per Ken B. End of entrance is incomplete. Landscaping is incomplete. Stop signs are missing. Rock piles in parking lot, green sidewalks, detention area incomplete and ADA signage is incomplete.
4/25/08 corrections required per Ken B - Port-a-pot still on site, heavy equipment on site, landscape incomplete at front, detention incomplete.
5/2/2008 Approved per Ken Bricker.. Remove Port A Pot off site
4/14/09 1 year warranty - corrections required per Laura Taylor - Tree Stakes should be removed. |