Building Permit/Final Inspection Status |
| Name |
Trendwest 3 & 4 |
| Number |
Grading-33874 |
| Drawing of Record Submitted |
|
| Electronic Drawing
of Record Submitted |
|
| Final Grading Report
Submitted |
|
| Date Scheduled |
|
| BUILDING
PERMIT RELEASE APPROVALS |
| Power |
|
| Water |
|
| Waste |
|
| Engineering |
|
| City Development Engineer |
|
| Landscaping |
|
| FINAL
INSPECTION RELEASE APPROVALS |
| Power |
5/24/06 Corrections required per Dennis Wright -- NOT READY. 6/5/06 BLDG 2 Approved per Dennis Wright. |
| Water |
05/16/2006 Corrections required per Kevin Condie.. 1. Missing valve by round about.2. Fire hydrant by plantation Drive, need to move just in back at side walk.3. Need to check wire, 4. Need to put arrow and size in valve collars 5. Need to check valves. 6. Meter by building need concrete collars.7. Hydrants need concrete collars. 6/6/06 Corrections required per Kevin C. - Test backflow on f ire system. Have plumber turn water on when ready. Need to check vavle on fire system.
06/09/2006 Approved per Kevin Condie.. For Building E ONLY.. CO on Building E Only |
| Waste |
05/18/2006. Corrections required per Glen Garland..Draw of Record incorrect 3 clenaouts on 6" line have been eliminated in front of bldg #1.No asphalt on side of bldg #3 going toward maint. bldg. have 3 cleanouts needing collars when asphalt finished.
06/08/2006 Approved per Glen Garland |
| Engineering |
6/13/06 Corrections Required per Carlos R. Clean up debris. Clean up gravel rock.
07/11/2006 Corrections required per Carlos. R.. NOT READY |
| City Development Engineer |
5/26/06 Corrections Required per Cathy H. General cleaning around gutters. Repair cracks and breaks in curbing on SE end. Clean off sidewalks and dirt curb accesses. Electronic dwg of record - needs to have ties from TBC and MH for locations of sewer clean outs.
06/09/2006 Approved per Brett B. |
| Landscaping |
5/26/06 Approved per Cathy H. |