Name   [ANB Financial]
Number   Grading-35554
Drawing of Record Submitted   09/28/2006..revised 10/05/2006
Electronic Drawing of Record Submitted   09/28/2006..revised 10/05/2006
Final Grading Report Submitted   09/28/2006
Date Scheduled   10/04/2006


BUILDING PERMIT RELEASE APPROVALS
Power  
Water  
Waste  
Engineering  
City Development Engineer  
Landscaping  


FINAL INSPECTION RELEASE APPROVALS
Power   10/4/06 Approved per Dennis Wright
Water   10/6/06 Approved per Tim Dotson
Waste   10/3/06 Corrections Required per Glen Garland. Missing street cleanout. Drawing of record does not match actual layout. 4/27/2012 Approved per Cathy H
Engineering   10/04/2006 Approved per Carlos Robles
City Development Engineer   10/04/2006 Corrections required per Ken Bricker.. Dumpster missing, trash in gutter,scaffolding standing on S/W,porta-a-potty in landscape area. 10/06/2006 Not Approved.. Fountain in front cannot be placed over sewer and storm lines. 10/31/2006 Corrections required per Cathy H.. Waiting on signed agreement 4/19/12 approved per Cathy H. Deed restriction recorded
Landscaping   10/04/2006 Corrections required per Ken Bricker.. Front and back landscape is incomplete.