Building Permit/Final Inspection Status |
| Name |
[Seven Hills Phase III] |
| Number |
Grading 27300 |
| Drawing of Record Submitted |
10/29/2004 |
| Electronic Drawing
of Record Submitted |
10/29/2004 |
| Final Grading Report
Submitted |
10/29/2004 |
| Date Scheduled |
11/02/04 |
| BUILDING
PERMIT RELEASE APPROVALS |
| Power |
5/12/04 PERMITS ONLY - approved per Dennis Wright. Power okay for permits only. |
| Water |
5/12/2004. Approved per Kevin Condie for permits only. |
| Waste |
5/12/2004. Permits only Approved per Zene. |
| Engineering |
05/18/2004. Permits only approved per Jay Sandberg. |
| City Development Engineer |
05/13/2004. Permits only approved per Larry Henderson. |
| Landscaping |
5/10/2004. Approved per Doug/Lynne for permits only. |
| FINAL
INSPECTION RELEASE APPROVALS |
| Power |
11/02/2004 Approved per Dennis Wright |
| Water |
02/04/2005 Approved per Kevin Condie Phase 3 |
| Waste |
11/03/2004 Approved Per Glen Garland |
| Engineering |
11/02/2004 Corrections required per Larry Henderson.. Remove construction materials from sidewalk on Tuweep Trim expansion joints, Seal cracks in curbs, Complete patch on 1140 North @ Tuweep. Ramp ends of sidewalk
11/16/2004 Approved per Larry Henderson
1/27/2005 Approved per Larry Henderson |
| City Development Engineer |
02/08/2005 Approved per Jay Sandberg |
| Landscaping |
01/28/2005 Approved Per Doug W. |