Family Dollar Distribution Center
JUC STATUS
Current Status   Obtaining Signatures
JUC 1st Review  
JUC 2nd Review   5/15/12
JUC 3rd Review  
JUC 4th Review  
JUC Approved  
JUC Comments:

5/8/12 JUC plans distributed for review. 5/15/12 JUC returned utility plans with comments from review. Make all corrections from each department. WHEN SITE PLAN AND CONSTRUCTION DRAWING REVIEW IS COMPLETE, may submit for approval (9 full sets and 8 JUC sets). 7/3/12 obtaining signatures from departments.
 
CONSTRUCTION DRAWING STATUS
Current Status   Under Review
1st Review  
2nd Review  
3rd Review  
4th Review  
Final Approval  
Construction Review Comments:

5/25/12 plans distributed for review PDF to Brett, Planning and Streets. 5/30/12 received review from planning. 5/30/12 received review from streets. 5/30/12 distributed plans to Planning (LANDSCAPING). 6/21/12 received plans from engineer. Received letter from Engineer. Received redlines. 6/21/12 distributed plans to Brett.