10/18/11 Pratt Engineering Representative did not attend JUC. Review comments were returned to JUC Coordinator.
1/17/12 JUC distributed plans (Revised plans).
1/24/12 (Revised plans) JUC returned utility plans with comments from 1st review. Make corrections. When civil site plan construction drawings have been submitted for review and comments from JUC have been address, submit for 2nd JUC review.
CONSTRUCTION DRAWING STATUS
Current Status
Under Review
1st Review
2nd Review
3rd Review
4th Review
Final Approval
Construction Review Comments:
2/10/12 distributed plans for review (CD to Brett, plans to Planning (Craig) and Streets (Randy).
2/14/12 received review from streets.
3/12/12 received review from planning (LANDSCAPE).
5/2/12 received review from streets.