Project Name   {Bomatics TI}
Complete Plans Submitted   8/4/04 (elec TI)
Sent For Structural Review  
1st Plan Review Completed   8/12/04
Returned From Arch / Engineer For Re-review  
Returned To Arch / Engineer For Futher Corrections  
Plan Review Approved   8/12/04
Permit Issued   10/7/04


General Comments Electrical plans submitted 8/4/04.Contractor notified 8/30,waiting for building permit app. to issue permit.Notified contractor permit needs to be issued and paid for 9/16/04.