City of St. George Development Services |
| Project Name |
{Coral Desert Applegate Homecare} |
| Complete Plans Submitted |
12/10/02 |
| Sent For Structural Review |
|
| 1st Plan Review Completed |
12/10/02 |
| Returned From Arch / Engineer
For Re-review |
12/24/02 |
| Returned To Arch / Engineer
For Futher Corrections |
1/14/03 |
| Plan Review Approved |
1/16/03 |
| Permit Issued |
2/21/03 |
| General Comments |