City of St. George Development Services |
| Project Name |
{Sprinkler Supply} |
| Complete Plans Submitted |
5/7/04 |
| Sent For Structural Review |
|
| 1st Plan Review Completed |
5/24/04 |
| Returned From Arch / Engineer
For Re-review |
|
| Returned To Arch / Engineer
For Futher Corrections |
|
| Plan Review Approved |
10/06/04 |
| Permit Issued |
11/29/04 |
| General Comments |
Plans submitted 3/5/04 not complete,soils report required,tried to make contact with contractor with phone number provided,no answer.Notified contractor that soils report is required for plan reveiw 3/8/04.Owner stopped project 3/16/04,plans returned to owner, he will re-submit when complete,plans re-submitted 5/7/04.Received approved siste plan 11/02/04,service size on building plan does not match approved site plan,tried to contact contractor 11/8/04-11/09/04. |