City of St. George Development Services |
| Project Name |
{Tonaquint Center - Phase 2- Lot 3} |
| Complete Plans Submitted |
2/4/04 |
| Sent For Structural Review |
|
| 1st Plan Review Completed |
2/18/04 |
| Returned From Arch / Engineer
For Re-review |
3/4/04 |
| Returned To Arch / Engineer
For Futher Corrections |
3/9/04 |
| Plan Review Approved |
3/17/04 |
| Permit Issued |
3/31/04 |
| General Comments |
Arch delivered response to city office,will forward to Sunrise Eng 3/4/04.Met with TM const. service size shown on approved site plan does not match with elec engineering on plans, working with contractor and power dept to resove issues.Sunrise Eng and I met with Clarence from Campbell Arch. 3/11/04 to resolve final issues,waiting for response from arch |