City of St. George Development Services |
| Project Name |
{Sandstone Village (shell only)} |
| Complete Plans Submitted |
9/16/03 ( shell only) |
| Sent For Structural Review |
|
| 1st Plan Review Completed |
10/15/03 (shell only) |
| Returned From Arch / Engineer
For Re-review |
|
| Returned To Arch / Engineer
For Futher Corrections |
|
| Plan Review Approved |
11/18/03 |
| Permit Issued |
12/3/03 |
| General Comments |
Partial plans submitted 9/16/03.Building Official approved fast track.Permit could be issued 11/18/03,waiting for owner to decide on sevice sizes.CD not complete, permit issued subject to complete CD being submitted. Comments from Willdan Project Log-->1st Rcd-9/19/2003; Out 1-10/15/2003; In 2-11/7/2003; Out 2-11/11/2003; In 3-11/13/2003; Out 3-11/18/2003; Status-Approved; Rvwd By-TRB |