Oval: START

Flow Charts

SUBMIT SITE PLAN TO ENERGY SERVICES OR DIXIE ESCALANTE FOR POWER DESIGN

Rounded Rectangle: POWER DESIGN MARKED ON SITE PLAN AND RETURNED TO ENGINEERING FIRM
Flowchart: Decision: IS AN ADDITIONAL REVEW REQUIRED?

YES

NO

Rounded Rectangle: JUC REVIEWS UTILITY PLAN AND PREPARES COMMENTS FOR JUC MEETING
(1 WEEK)
Oval: CONSTRUCTION PLAN APPROVAL PROCESS

CIVIL ENGINEER MAKES CHANGES TO PLAN AND RE-SUBMITS 8 COPIES TO JUC FOR REVIEW

ADD POWER, WATER AND SEWER DESIGN TO UTILITY PLAN AND SUBMIT 8 COPIES TO JUC FOR 1ST REVIEW

CIVIL ENGINEER ATTENDS FOLLOWING JUC MEETING TO RECEIVE COMMENTS FROM 1ST REVIEW

Rounded Rectangle: JUC REVIEWS UTILITY PLAN AND PREPARES COMMENTS FOR JUC MEETING
(1 WEEK)

CIVIL ENGINEER MAKES CHANGES TO PLAN AND RE-SUBMITS 8 COPIES TO JUC FOR 2ND REVIEW.  GAS, PHONE & CABLE TV DESIGNS ARE ADDED.

CIVIL ENGINEER ATTENDS FOLLWING JUC MEETING TO RECEIVE COMMENTS FROM 2ND REVIEW

Rounded Rectangle: JUC REVIEWS UTILITY PLAN AND PREPARES COMMENTS FOR JUC MEETING
(1 WEEK)
Folded Corner: UTILITY PLANS FOR JUC REVIEW NEED TO BE SUBMITTED ALONG WITH 4 SITE/SUBDIVISION CONSTRUCTION SETS IN PLAT & PLAN WEEKLY MEETING.  CALL 627-4120 TO SCHEDULE AN APPOINTMENT.

1

1

1

Rounded Rectangle: CITY RESPONSIBILITY

DEVELOPER RESPONSIBILITY

Folded Corner: NOTES
Flowchart: Decision: DECISION
Oval: START / FINISH

LEGEND

Rounded Rectangle: UTILITY PLANS ARE DISTRIBUTED AT TUESDAYS JUC MEETING
Folded Corner: IF THE CIVIL ENGINEER FAILS TO ATTEND THE JUC MEETING TO RECEIVE COMMENTS FROM REVIEW, PLANS ARE COLLECTED AND HELD UNTIL THE FOLLOWING JUC MEETING.

2

Joint Utility Committee Review Process

Detailed Review Process